Fleetwood High School - Sports Pitches
Project: Fleetwood High School Sports Pitches
Client: Lancashire County Council
Contract: Fleetwood High School PFI
Scope: Achieve All Year-Round Use of Pitches
Benefit: Works carried out at PFI Provider’s cost, 15 months earlier than planned
The Issue
Poor drainage of sports pitches since the start of the PFI contract in 2003 meant they were unusable for most of the year even in drier periods as repeated waterlogging led to poor surface quality. This problem was compounded by irregular maintenance.
Our Brief
We were asked by Lancashire County Council who are the PFI Authority to investigate, carry out site surveys and make recommendations to achieve all year availability of the sports pitches.
Our Solution
Our detailed inspection and analysis of both the original PFI contracts and the site identified the following problems:
Armed with this information, our team of specialists designed a site-wide solution. Although the SPV initially rejected the proposals, following further negotiation they agreed that the PFI provider would indeed fund fully the scheme of improvements, bringing the following benefits:
Benefit
Our involvement ensured that all works were carried out at the PFI Provider’s cost, with pitches available 15 months earlier than planned. Sports fields were made available for an extensive PE curriculum all year round, and an additional site was created for both quiet and raucous play during break times.