ASA Hard FM Contract Termination
Project: ASA Hard FM Contract Termination
Client: Archbishop Sentamu Academy
Contract: Hard FM and Lifecycle
Scope: Termination of Hard FM & Lifecycle
The Issue
Archbishop Sentamu Academy was constructed in 2011 under the building schools for the future scheme through a Design and Build contract. The operational contract, including Hard FM and Lifecycle, was held by the Academy, the Council, and the Local Education Partnership (LEP) who provided the service. Excessive risk pricing and onerous KPI’s however made this contract poor value for money.
Our Brief
Hard FM and Lifecycle costs respectively were far higher than expected for this type of facility and they caused the Academy serious financial hardship. The Academy had approached the Council about this, and with their full support, commissioned us to review the contracts with the aim of reducing their combined cost.
Our Solution
We undertook a full review of both contracts as well as a comprehensive statutory compliance survey. We quickly devised a strategy for removing the Academy from both Hard FM and Lifecycle contracts and then negotiated a new contract. To achieve this, we did the following:
Our Achievements
Total Client Savings
A 27% reduction in contract costs which equates to a six-figure saving per annum to the Academy.